第一篇:110kV龙口牵引站配套线路工程工程竣工监理初检方案

JZLX9 输电线路工程监理初检方案

110kV龙口牵引站配套线路工程

竣工监理初检方案

江西科能监理公司<27>监理项目部

202_ 年 6 月

一、工程概述

1.1工程规模及建设情况

110kV龙口牵引站配套线路工程,分为两段,由两个220kV变电站分别向龙口牵引站送电。它们分别是赣县的山田变——龙口牵引站,兴国县的埠头变——龙口牵引站。山田——龙口线路长27.543公里,共84基铁塔,单回架设。埠头——龙口线路全长18.583公里,共55基铁塔,单回架设。共使用三种基础形式,分别是直柱全掏挖基础、人工挖孔桩基础、板式基础。目前,本工程已全部完成,本次将按国家规范要求进行竣工监理初检验收。1.2工程参建单位 建设单位:赣州供电公司

设计单位:赣州宏远电力勘测设计院 施工单位:江西省送变电建设公司

监理单位:江西省科能工程建设咨询监理有限公司

二、验收依据

2.1国家标准《110~500kV架空送电线路工程施工及验收规范》(GB5023-202_)

2.2《110kV~ 500kV架空电力线路工程施工质量及评定规程》(DL/T5168-202_)

2.3《国家电网公司工程建设质量管理规定》(国家电网基建<202_>699号)

2.4《国建电网公司输变电工程达标投产考核办法》(国家电网基建

<202_>255号)

2.5《工程建设标准强制性条文电力工程部分》(202_年版)2.6经批准的工程设计文件及施工图

三、验收条件

1.施工单位按设计和规范要求完成相应施工无明显缺陷和遗留项目。2已完工程经过施工项目部三级自检合格、具备申报验收条件。3.施工单位应提交的竣工资料基本整理完毕、合格有效且满足验收条件。

4.监理单位收到施工项目部填报的《工程竣工验收申请表》及相关自检记录。

四、验收组织机构及人员职责 4.1验收组织机构设置 检查组长:任昌煊 副组长:施根才 成员:冯石毅、梁凯 配合:施工项目部2人 4.2验收人员职责:

任昌煊负责竣工资料内容的验收检查。

施根才负责组织检查组成员对现场情况进行验收检查。各成员按负责人分工认真做好本职工作。

五、验收时间安排:

验收时间暂定202_年6月9日—202_年6月10日。

六、验收要求 6.1验收总体要求

⑴初验收坚持现场检查与资料核查相结合,全面检查与重点抽查相结合的原则,既要检查现场实体质量,也要核查相关资料情况;既要重点抽查一些项目,也要对验收范围内的项目做全面检查,做到验收覆盖面100%,不漏项。

⑵各验收小组要根据分工和工程施工完成情况,合理安排工作进度,保证验收工作安全、有序进行。

⑶各验收人员要充分熟悉设计图纸、技术规范书和相关专业的有关标准、规范,熟悉材料/设备性能、参数和设备装置的原理。⑷验收用仪器仪表使用前应核查符合相关要求,保证完好、有效。验收人员必须严格执行验收规范,按照设计图纸认真验收、严格把关,确保验收质量。要认真填写质量检查验收记录,发现问题先与施工配合人员充分沟通,然后及时填写“工程质量检查及缺陷处理记录”,并且交给施工单位进行整改。6.2验收内容

⑴对铁塔主要检查架线后铁塔倾斜、螺栓的紧固率、螺栓的防盗防松、塔脚保护帽等。

⑵对接地电阻进行测量,对接地装置的埋深和接地体的焊接质量以及接地引下线安装工艺进行检查。

⑶附件安装部分,主要检查金具、绝缘子、开口销、闭口销、R销的规格数量、穿向,跳线引流线及安装,跳线制作工艺,跳线弛度及对

塔身电气距离,绝缘子串倾斜、防震锤、护线条、线夹、均压环安装位置及工艺,避雷线的放电间隙等。

⑷对导、地线和光缆的弧垂检查,主要检查导、地线的弧垂,相间弧垂误差和子导线弧垂误差,导线对交叉跨越物和对地距离等。⑸对OPGW光缆施工质量的检查,主要检查金具的规格、数量和附件安装工艺,接地盒、余缆盘、耐张直通引流和分断下引光缆的安装质量等。

⑹地面工程,主要检查塔基边坡、防沉层、排水沟、护坡或挡土墙、护面以及弃土处理、植被恢复等进行检查。

⑺工程资料检查要按省电力公司《输变电工程竣工文件归档管理办法(试行)》(赣电总〔202_〕5号)进行全面检查,主要检查资料的完整性、有效性、真实性、准确性和规范性。

七、质量验评

7.1本次初检工作与工程质量验评工作结合进行。按照已审批的《110kV龙口牵引站配套线路工程质量验评范围划分表》。初检中重点抽检的分项工程个数要求≥30%。

7.2检查完成后,由检查组及时提出检查报告,对检查结果作出评价。对存在的问题提出处理意见和整改要求,整改完毕经监理复查、签证、确认合格后,监理部提出监理初检报告,上报项目建设管理单位,并书面向项目建设管理单位提出竣工预验收申请报告,请建设管理单位组织进行工程竣工预验收。

第二篇:乐安工程监理初检方案(范文)

监理初检方案

工程名称:220kV乐安变电站扩建工程

项目监理部(章): 总监理师:徐新玲

潍坊电力咨询设计有限公司

220kV乐安变电站扩建工程监理初检方案

220kV乐安变电站扩建工程由东营方大电力设计规划有限公司设计,山东送变电工程公司施工,潍坊电力咨询设计有限公司监理,东营供电公司为集团公司委托管理单位。根据山东送变电工程公司向我单位提交的工程初步竣工验收申请,我公司定于202_年11月25日对乐安变电站扩建工程进行工程初步竣工预验收,特制定此方案。

一、工程概述:

1、工程规模及建设情况:

为满足广饶县经济社会发展需要,实施扩建220kV乐安变电站。本期规模:安装1台SSZ-180/220变压器;电容器容量分别是10008Kvar、20016 Kvar各一组;GIS双母线配电装置:220kV主变进线间隔一个,备用间隔一个;110kV主变进线间隔一个出线间隔四个。35kV单母线配电装置:主变进线柜一面,出线柜六面。

2、工程参建单位: 建设单位:东营供电公司

设计单位:东营方大电力设计规划有限公司 施工单位:山东送变电工程公司 监理单位:潍坊电力咨询设计有限公司 运行单位:东营供电公司

二、验收依据:

1、中华人民共和国《 工程建设标准强制性条文》电力工程部分(202_年版建标【202_】102号)。

2、中华人民共和国《 工程建设标准强制性条文》房屋建筑部分(202_年版建标【202_】219号)。

3、中华人民共和国《 工程建设标准强制性条文》工业建筑部分(202_年版建标【202_】)。

4、国家电网公司《国家电网公司工程建设质量管理规定(试行)》(国家电网基建【202_】699号)。

5、《电气装置安装工程质量检验及评定标准》(DL/T5161.1-5161.17-202_)。

6、《电力建设施工质量验收及评定规程》(DL/T5210.1-202_)。

7、《国家电网公司十八项电网重大反事故措施》(试行)(国家电网生技【202_】400号)。

8、国家电网公司《电力建设工程施工技术管理导则》(国家电网工【202_】153号)。

9、电力建设工程质量监督总站《电力建设工程质量监督规定》。

10、电力建设工程质量监督总站《电力建设工程质量监督检查典型大纲》(火电、送变电部分)电建质监【202_】57号。

11、国家电网公司文件“关于转发《电力建设房屋工程质量通病防治工作规定》的通知”(工建质【202_】

202号)。

12、《电力建设工程施工技术管理导则》(国家电网工【202_】153号)。

13、《国家重大建设项目文件归档要求与档案整理规范》(DA/T28-202_)。

14、《国家电网公司工程建设质量管理规定(试行)》(国家电网基建【202_】699号)。

15、《国家电网公司工程建设质量管理责任考核办法(试行)》(国家电网基建【202_】674号)。

16、《国家电网公司输变电工程达标投产考核办法》的通知(国家电网基建(202_)146号);

17、《国家电网公司输变电优质工程评选办法》(国家电网基建质量【202_】148号)。;

18、《国家电网公司输变电工程施工工艺示范手册》(变电站工程分册土建部分、电气部分、送电工程分册)。

19、中国电力优质工程评选办法(202_版)。

20、《国家电网公司输变电工程标准化施工手册》(变电站工程分册、送电工程分册)。

21、《关于强化输变电工程施工过程质量控制数码照片采集与管理的工作要求》的通知(基建质量[202_]322号);

22、《110kV及以上送变电工程启动及竣工验收规程》(DL/T782-202_)。

23、中华人民共和国国家标准GB50202-202_《地基与基础工程施工质量验收规范》。

24、中华人民共和国国家标准GB50204-202_《混凝土结构工程施工质量验收规范》。

25、中华人民共和国国家标准GBJ147-90《电气装置安装工程高压电器施工及验收规范》。

26、中华人民共和国国家标准GBJ148-90《电气装置安装工程电力变压器、油浸电抗器、互感器施工及验收规范》。

27、中华人民共和国国家标准GBJ149-90《电气装置安装工程母线装置施工及验收规范》。

28、中华人民共和国国家标准GB50150-91《电气装置安装工程电气设备交接试验标准》。

29、中华人民共和国国家标准GB50168-92《电气装置安装工程电缆线路施工及验收规范》。30、中华人民共和国国家标准GB50169-92《电气装置安装工程接地装置施工及验收规范》。

31、中华人民共和国国家标准GB50171-92《电气装置安装工程盘、柜及二次回路结线施工及验收规范》。

32、山东电力集团公司SDJ69-87《电力建设施工及验收规范》。

33、中华人民共和国国家标准GBJ50300-202_《建筑工程施工质量验收统一标准》。

34、中华人民共和国国家标准GB/T50328-202_《建设工程项目管理规范》。

35、山东电力集团公司《110kV~1000kV变电(换流)站土建工程施工质量验收及评定规程》(Q/GDW183-202_)。

36、山东电力集团公司文件:鲁电集团供【1999】176号关于下发《新建、扩建变电站生产验收管理办法》(试行)的通知。

37、山东电力集团公司文件:鲁电安【1998】177号《新建变电站投运前安全监察规定》。

38、国家电力公司文件:《防止电力生产重大事故二十五项重点措施》。

39、制造商提供的产品出厂合格证书、检查试验报告。

40、设计图纸、资料、设计变更通知书和厂家及有关方面签订的技术资料。

41、施工单位提出经有关单位认可的施工联系单、设计变更。

42、施工单位与本工程签订的合同或协议。

三、验收范围及条件:

(一)、验收范围:

1、土建部分:

1)所区设备、支架基础、架构、电缆沟、电缆支架、电缆盖板等。

2、变电一次部分:

1)、主变压器本体及附件、主变套管、主变消防系统等附属配套设备。2)、110kVGIS设备、防雷设施、接地网及设备联线。3)、220kVGIS设备、防雷设施、接地网及设备联线。

4)、35kV开关柜(含电容器装置)的开关、刀闸、CT、PT、避雷器、母线、设备联线、高压电缆、设备接地装置、接地网、消弧线圈。

5)、安全工器具、设备标识牌、安全警示牌及相关设施。

3、变电二次部分:

1)、220及110kV间隔保护系统和微机监控系统、隔离开关的闭锁回路、母线接地刀闸的闭锁回路、电能表及相关设备。

2)、35kV高压开关的保护系统及相关设备。

3)、保护盘、端子箱、机构箱、检修电源箱的安装、接地、封堵、标示牌;电缆整理、走向牌、接线。4)、微机五防装置。

4、工程资料:

1)、工程资料移交清单、备品备件移交清单、设备开箱检查记录、设计图纸及技术资料。

2)、制造厂提供的图纸、技术说明书、出厂证明书及备品备件,原材料及半成品等的出厂质量合格证明或检查试验记录。

3)、安装技术记录,调整试验、化验记录,测试、试验报告,接地装置的接地电阻测量记录,竣工图纸等。

(二)、验收条件:

1、施工单位已按设计图纸和变更及合同要求完成工程的全部施工内容。

2、工程已完成三级自检并合格,并已向监理项目部提报验收申请。

3、施工单位应提交的工程策划,过程资料,竣工资料基本整理完毕,可以满足验收需要。

4、监理项目部已收到施工项目部填报的《工程竣工申请报验单》及自检记录。

四、验收组织机构及人员职责:

1、验收组织机构设置:

1.1、成立220kV乐安变电站扩建工程初检验收领导小组。组长: 成员:

1.2、下设四个验收小组。

土建工程组:组长: 成员: 安装工程组:组长: 成员: 工程资料组:组长: 成员:

2、验收组织人员职责:

2.1、组长、副组长职责:负责统筹安排初验收工作,协调处理施工、运行、监理、设计、供货厂家等各方关系及验收中出现的重大事宜、争议。负责组织召开每日的验收汇总会,听取各验收小组的工作汇报,总结每日验收工作,对验收中发现的缺陷提出整改指导意见,督促消缺,审核确认验收记录及验收报告。2.2、各验收小组组长职责:组织本小组人员按验收范围及要求进行各专业工程验收,搜集、汇总验收缺陷及问题,消缺完成后,组织人员复查确认,填写验收记录和验收报告。

2.3、各验收小组副组长职责:负责本小组人员(主要是运行人员)的召集、管理、组织参与验收工作,提出验收缺陷和问题,消缺完成后,参与复查、确认。

2.4、各验收小组组员职责:在小组长的领导下,具体负责各自范围内的验收工作及消缺复查工作。2.5、各验收小组配合人员职责:对各小组验收工作进行全面配合,包括资料提供,工具提供、后勤保障、配合具体的作业工作等。

3、验收资源配置:

五、验收时间安排:

202_年11月23日9时至16时。

六、验收要求:

1、验收总体要求:

(1)、本次验收要求现场检查与资料核查相结合,重点检查工程施工中是否按照施工图纸和工艺标准要求进行施工,过程资料是否和实体施工一致,要求对本工程范围内的工程项目进行全面检查,做到验收覆盖面100%,不漏项。

(2)、各验收小组要根据分工和工程完成情况,合理安排验收工作进度,保证验收工作安全、有序,争取按计划完成验收工作,给按时送电做好准备。

(3)、各验收人员要充分熟悉设计图纸、技术规范和相关的有关的标准规范,熟悉材料/设备性能、参数和设备装置的原理,从而判定工程是否符合要求。

(4)、验收人员必须要严格执行验收规范,按照实际图纸认真验收,严格把关,确保验收质量,要认真填写质量检查验收记录,发现问题先与施工配合人员沟通,然后及时填写“工程质量检查及缺陷处理记录”。此记录要及时整理,及时交施工单位及时进行消缺。

(5)、验收前,施工单位应向验收组提供下列主要资料及文件: 1)、主要施工技术资料。2)、主要施工技术记录。3)、质量检验、调试记录。4)、出厂资料、试验资料。5)、材料/构配件开箱记录。

6)、制造厂提供的出厂原始资料,即产品说明书、出厂试验记录、合格证及出厂图纸等。

2、各单位工程验收要求:

七、质量验评及竣工初检验收报告。

在施工单位完成三级验收基础上,我公司组织各相关人员分别对施工现场及工程资料进行检查,对现场的土建外观质量情况、设备安装情况、相关尺寸偏差及调试、试运行情况进行检查预验收,对工程施工过程资料及设备调试、试验资料进行检查预验收。

1、本次初检工作与工程质量验评工作结合进行。按照已审批的《变电站工程质量验评范围划分表》进行验评。

2、初检工作计划于 11月23日结束。消缺完成,并得到验收小组的确认。

3、各验收小组提出书面初检意见并汇总成初检报告,并上报业主。

八、安全措施。

1、验收工作组设专职安全负责人,各验收小组安全员由小组负责人兼职,对各项验收工作进行监护,及时纠正不安全行为,不得违章作业,违章指挥。

2、验收开始前,安全负责人对验收工作中有关安全注意事项进行交待,验收期间不得违反工作纪律。

3、所有验收工器具必须符合安全规范标准,必须检验合格后方可是用。

4、专职安全负责人要集中精力做好监护工作,不得兼任其他工作。

潍坊电力咨询设计有限公司

202_年11月23日

第三篇:输电线路工程监理初检方案

JZLX9 输电线路工程监理初检方案

XXX220kV接入系统(线路工程

(基础分部工程)

监理初检方案

XXX(线路)工程 监理项目部 202_ 年 5 月22日 批准:审核:编写:年 月年 月年 月

目 录 工程概述-----1 1.1 工程规模及建设情况--------------------1 1.2 工程参建单位--------------------------1 2 验收依据-----1 3 验收范围及条件------------------------------2 3.1 验收范围------------------------------2 3.2 验收条件------------------------------2 4 验收组织机构及人员职责----------------------2 4.1 验收组织机构设置----------------------2 4.2 验收人员职责--------------------------2 4.3 验收资源配置--------------------------3 5 验收时间安排-3 6 验收要求-----3

6.1 验收总体要求--------------------------3 6.2 基础分部(单位)工程验收要求------------4 7 质量验评及竣工初检验收报告------------------4 8 安全措施-----5

1、工程概况

1.1工程规模及建设情况

本工程自新XXX220千伏变电站门构起,新建单回线路长度为12.001km。

导、地线型号:导线型号为1×LGJ-400/35型钢芯铝绞线。本工程新建线路架设两根地线,其中一根为24芯OPWG光缆,另一根为GJ-80型镀锌钢绞线。

杆塔:本工程采用自立式铁共31基

基础:自立式铁塔采用台阶式钢筋混凝土基础。接地:全线杆塔逐基接地。

1.2 工程参建单位

项目法人:XXX有限公司 建设管理单位:XXX 监理单位:XXX电力工程监理有限公司 设计单位:XXX 施工单位:XXX公司 验收依据

(1)《国家电网公司工程建设质量管理规定》(国家电网基建〔202_〕699号)。(2)《国家电网公司输变电工程达标投产考核办法》(国家电网基建〔202_〕146号)。(3)《国家电网公司输变电工程施工工艺示范手册》[202_]135。(4)《工程建设标准强制性条文电力工程部分》(202_年版)。

(5)《关于强化输变电工程质量控制数码照片采集与管理的工作要求》国家电网基建质量[202_]322号

(6)《关于印发国家电网公司建设项目管理办法(试行)的通知》国家电网办[202_]250号

(7)《国家电网公司电力建设工程施工质量监理管理办法》国家电网基建[202_]160号(8)《国家电网公司输变电工程质量通病防治工作要求及技术措施》国家电网基建质量19号

(9)《国家电网公司工程建设质量管理规定》(试行)国家电网基建[202_]699号(10)《国家电网公司工程建设质量责任考核办法(试行)国家电网基建[202_]674号

(11)《输变电工程建设标准强制性条文实施管理规程》Q/GDW248-202_(12)《混凝土结构工程施工质量验收规范》GB 50204-202_(13)《110KV—500KV架空送电线路施工及验收规范》GB 50233-202_(14)本工程的设计图纸及业主有关规定及设备出厂资料。验收范围及条件

3.1 验收范围

本次初检的范围包括本工程各分部工程的实体及相关资料。(基础工程、杆塔组立、导、地线架设)

3.2 验收条件

(1)施工单位按设计和规范要求完成相应施工,无明显缺陷和遗留项目。(2)已完工程经过施工项目部三级自检合格,造价人才网具备申报验收条件。(3)施工单位应提交的验收资料基本整理完毕,齐全有效,能够满足验收条件。(4)监理单位收到施工项目部填报的《工程报验单》及相关自检记录。验收组织机构及人员职责

4.1 验收组织机构设置

成立XXX(线路)工程初检验收组”。验收领导小组: 组 长:XXX 副组长:XXX 验收工作组成员:XXX、XXX、XXX、XXX、XXX、4.2 验收人员职责

(1)初检验收组组长、副组长职责:负责统筹安排初验收工作,协调处理施工、运行、监理、设计、厂家等各方关系及验收中出现的重大事宜、争议,负责组织召开每日的验收汇总会,听取验收小组的工作汇报,总结每日验收工作,对验收中发现的缺陷提出整改指导意见,督促消缺,审核确认验收记录及验收报告。

(2)验收小组组长职责:组织本小组人员按验收范围及要求进行各专业工程验收,搜集、汇总验收缺陷及问题,消缺完成后,组织人员复查确认,填写验收记录及验收报告。(3)验收小组副组长职责:负责本小组内验收人员(主要是运行人员)的招集、管理工

作,组织、参与验收工作,提出验收缺陷及问题,消缺完成后,参与复查、确认。(4)验收小组组员职责:在小组组长的领导下,环保人才网具体负责各自范围的验收工作及消缺复查工作。

(5)验收小组配合人员职责:对小组验收工作进行全面配合,包括资料提供、工器具提供、后勤保障、配合具体的作业工作等。

4.3 验收资源配置

检测仪器:经纬仪一台、测距/测高仪一台、钢卷尺30M一把,游标卡尺2把,接地电阻测试仪一台,土建施工检查工具一套

交通车辆:监理单位和施工单位越野车各一辆

规程规范:《输变电工程建设标准强制性条文实施管理规程》Q/GDW248-202_ 《工程建设标准强制性条文电力工程部分》(202_年版)。

《混凝土结构工程施工质量验收规范》GB 50204-202_ 《110KV—500KV架空送电线路施工及验收规范》GB 50233-202_ 本工程的设计图纸及业主有关规定及设备出厂资料 验收时间安排

验收时间暂定202_年05月20日~05月23日,验收要求

6.1 验收总体要求

(1)初验收坚持现场检查与资料核查相结合,全面检查与重点抽查相结合的原则,既要检查现场实体质量,也要核查相关资料情况,既要重点抽查一些项目,也要对验收范围内的项目做全面检查,做到验收覆盖面100%,不漏项。

(2)各验收小组要根据分工和工程施工完成情况,合理安排工作进度,保证验收工作安全、有序进行。

(3)各验收人员要充分熟悉设计图纸、技术规范书和相关专业的有关标准、规范,熟悉材料/设备性能、参数和设备装监理工程师论坛置的原理。

(4)验收用仪器仪表使用前应核查符合相关要求,保证完好、有效。

(5)验收人员必须严格执行验收规范,按照设计图纸认真验收,严格把关,确保验收质量。要认真填写质量检查验收记录,发现问题先与施工配合人员充分沟通,然后及时填写“工 3

程质量检查及缺陷处理记录”。此记录表每天汇总一次,交施工单位及时进行消缺。(6)验收前,施工单位应向验收组提供下列主要资料及文件: 1)主要施工技术资料。2)主要施工技术记录。3)质量检验记录。

4)原材料出厂资料、试验资料。5)材料进厂记录。

6)制造厂提供的出厂原始资料,即产品说明书、出厂试验记录、合格证及出厂图纸等。

6.2 基础分部(单位)工程验收重点及要求

基础工程

1、地脚螺栓露出基面高度

2、混凝土强度

3、底版断面尺寸

4、基础埋深

5、立柱断面尺寸

6、钢筋保护层厚度

7、混凝土表面质量

8、整基基础中心位移

9、整基基础扭转

10、回填土

11、基础根开及对角线尺寸

12、同组地脚螺栓中心与立柱中心偏移

13、基础顶面高差

14、其他 质量验评及竣工初检验收报告

(1)本次初检工作与工程质量验评工作结合进行。按照已审批的《本工程质量验评范围划分表》进行验评。初检中重点抽检的分项工程个数要求≥30%。

(2)初检工作结束,消缺完成并经验收小组复查确认后,由监理根据初检数据核实线路分项工程、分部工程、单位工程的质量等级,并形成验评报告。

(3)初检工作完成后,各验收小组提出书面初检意见,最后形成初检报告,并上报业主。安全措施

(1)验收前,验收组要向验收人员交代安全全注意事项,向验收人员进行交底,说明哪些工作需要验收人员互相之间配合完成。

(2)全体验收人员正确佩戴安全帽,高处验收作业必须正确使用安全带,安全带应系在牢固的构件上,杆塔上验收作业转位时,不得失去安全带的保护,杆塔上验收作业配备专人协助和监护。

(3)全体验收人员验收中要注意成品保护。

第四篇:风电工程监理初检方案

JZLB9 变电站工程监理初检方案

变电站工程

监理初检方案

监理项目部(加盖监理项目部公章)

年 月

批准:(总监理工程师)年 月 日

审核:(总监代表或专业组长)年 月 日

编写:(专业监理工程师)年 月 日

1工程概述 ·······································································································································167 1.1 工程规模及建设情况 ············································································································167 1.2 工程参建单位·······················································································································167

2验收依据 ·······································································································································167

3验收范围及条件 ·····························································································································167 3.1 验收范围······························································································································167 3.2 验收条件······························································································································168

4验收组织机构及人员职责 ···············································································································168 4.1 验收组织机构设置················································································································168 4.2 验收人员职责·······················································································································168 4.3 验收资源配置·······················································································································169

5验收时间安排 ································································································································169 6

验收要求 ·······································································································································169 6.1 验收总体要求·······················································································································169 6.2 各分部(单位)工程验收要求 ······························································································169 7

质量验评及初检报告 ······················································································································170 8

安全措施 ·······································································································································170 9

附表 ··············································································································································171

1工程概述

1.1 工程规模及建设情况

【编写说明】 可参照设计文件,简要阐述建设规模情况,结合实际工程进度,简述拟验收部分工程实施情况。

1.2 工程参建单位

【编写说明】 列举与本工程相关的各参建单位,单位名称确保准确。验收依据

【编写说明】 国家(行业)颁发的现行有关标准、规程和规范;本工程设计文件(含设计变更);建设单位、业主项目部下达的有关文件、规定;建设单位与施工、物资供应承包商签订的合同;设备出厂资料。

【示例】(1)《国家电网公司工程建设质量管理规定》(国家电网基建〔202_〕699号)。(2)《国家电网公司输变电工程达标投产考核办法》(国家电网基建〔202_〕255号)。(3)《国家电网公司输变电工程施工工艺示范手册(202_年版)》。(4)《工程建设标准强制性条文电力工程部分(202_年版)》。(5)《电气装置安装工程电气设备交接试验标准》(GB 50150—202_)。(6)《电气装置安装工程电缆线路施工及验收规程规范》(GB 50168—202_)。

(7)本工程的设计图纸及业主有关规定。…… 验收范围及条件

3.1 验收范围

【编写说明】 明确描述本次初检的具体验收范围(可按单位、分部、分项设置)。

【示例】

3.1 本次初检的范围

3.1.1 电气安装工程

包括下列部分的工程实体及相关资料:(1)220kV配电装置。(2)主控通信楼。

(3)35kV站用备用电源等。……

3.1.2 土建工程

包括下列部分的工程实体及相关资料:(1)构、支架。

(2)设备基础、防火墙、场平、道路、电缆沟(本期范围)。(3)室内外、排水系统、污水处理系统。(4)室内外生活给水系统、消防给水系统。(5)室内外采暖、通风系统。(6)室内外照明系统(本期范围)。(7)继电小室、交直流室。(8)主控通信楼、水泵房。

(9)蓄水池、事故油池(本期范围)。(10)消防火灾报警系统。……

3.2 验收条件

【编写说明】 描述是否具备初检验收规定比例,监理初检前的各项程序是否完成。【示例】(1)施工单位(施工、安装、调试)按设计和规范要求完成相应施工、安装、调试工程,无明显缺陷和遗留项目。

(2)已完工程经过施工项目部三级自检合格,具备申报验收条件。

(3)工程各专业应提交的竣工资料基本整理完毕,齐全有效,能够满足验收条件。(4)监理单位收到施工项目部填报的《工程竣工报验单》及相关自检记录。……

4验收组织机构及人员职责

4.1 验收组织机构设置

【编写说明】根据验收范围和验收工作内容,设置合理的验收组织机构。【示例】 4.1 成立“××工程初检验收组”

(1)验收领导小组: 组

长:××

副组长:××

×× ××(2)验收工作组: 1)资料验收小组:

长:×× 副组长:××

员:××

合:施工单位若干人

2)现场验收小组(按专业设置): 组

长:×× 副组长:×× 组

员:××

合:施工单位若干人 ……

4.2验收人员职责

【编写说明】对验收人员分层描述岗位职责。

【示例】

(1)初检验收组组长、副组长职责:负责统筹安排初验收工作,协调处理施工、运行、监理、设计、厂家等各方关系及验收中出现的重大事宜、争议,负责组织召开每日的验收汇总会,听取各验收小组的工作汇报,总结每日验收工作,对验收中发现的缺陷提出整改指导意见,督促消缺,审核确认验收记录及验收报告。

(2)各验收小组组长职责:组织本小组人员按验收范围及要求进行各专业工程验收,搜集、汇总验收缺陷及问题,消缺完成后,组织人员复查确认,填写验收记录及验收报告。(3)各验收小组副组长职责:负责本小组内验收人员(主要是运行人员)的召集、管理工作,组织、参与验收工作,提出验收缺陷及问题,消缺完成后,参与复查、确认。

(4)各验收小组组员职责:在小组组长的领导下,具体负责各自范围的验收工作及消缺复查工作。

(5)各验收小组配合人员职责:对各小组验收工作进行全面配合,包括资料提供、工器具提供、后勤保障、配合具体的作业工作等。

4.3验收资源配置

【编写说明】 验收所需的设备、交通车辆、通信工具、检测、测量、试验设备、规程、规范等技术文件。5 验收时间安排

【编写说明】 根据工程进度安排验收和消缺时间。【示例】

验收时间暂定××年××月××日~××月××日,消缺及复检时间××年××月××日~××月××日。6 验收要求

6.1 验收总体要求

【编写说明】对验收工作的通用要求,用于指导验收各小组的实际工作。从策划、准备情况、具体要求等方面列举。【示例】

(1)初验收坚持现场检查与资料核查相结合,全面检查与重点抽查相结合的原则,既要检查现场实体质量,也要核查相关资料情况,既要重点抽查一些项目,也要对验收范围内的项目做全面检查,做到验收覆盖面100%,不漏项。

(2)各验收小组要根据分工和工程施工完成情况,合理安排工作进度,保证验收工作安全、有序进行。

(3)各验收人员要充分熟悉设计图纸、技术规范书和相关专业的有关标准、规范,熟悉材料/设备性能、参数和设备装置的原理。

(4)验收用仪器仪表使用前应核查符合相关要求,保证完好、有效。

(5)验收人员必须严格执行验收规范,按照设计图纸认真验收,严格把关,确保验收质量。要认真填写质量检查验收记录,发现问题先与施工配合人员充分沟通,然后及时填写“工程质量检查及缺陷处理记录”。此记录表每天汇总一次,交施工单位及时进行消缺。(6)验收前,施工单位应向验收组提供下列主要资料及文件:

1)主要施工技术资料。2)主要施工技术记录。3)质量检验,调试记录。4)出厂资料、试验资料。

5)材料/构配件/设备开箱记录。

6)制造厂提供的出厂原始资料,即各设备的产品说明书、出厂试验记录、合格证及出厂图纸等。

……

6.2各分部(单位)工程验收要求

【编写说明】一般可按土建、电气等几部分(包括但不限于划分内容)分别描述各分部(单位)工程中具体内容和项目,便于指导监理人员现场的验收及评价工作。

【示例】

6.2.1 一次设备验收重点及要求

(1)总的要求。电气设备安装固定牢固、可靠;垂直度、水平度、安装尺寸偏差符合规范要求;设备各部件完好无损;电气连接可靠,接触良好,密封良好,不渗油、不漏气,油气技术指标符合要求;设备无锈蚀,油漆层或外镀层完整,相色标志正确,设备接地良好,各种电气距离满足要求。(2)高压电抗器。

1)电抗器本体、冷却器装置及所有附件应清洁,无渗油,各处密封垫平整、无裂纹。

2)油漆均匀完整,相序标志清晰正确,接地可靠。3)电抗器顶盖无遗留杂物。

4)储油柜、冷却装置、呼吸器等油系统上的阀门均应打开,且指示正确,各放气塞排气无残留气体,事故排油设施完好。

5)高低压侧套管引线接头螺栓紧固,平垫、弹簧垫齐全平整。

6)储油柜和充油套管的油位、油色应正常,储油柜油标上的温度指示线应清晰、准确或者油位指示器指示正常。

7)呼吸器畅通,硅胶无受潮变色。

8)瓦斯继电器和温度计应完整无损,防雨水措施良好,引出线完好,固定可靠,指示正确,校验合格,整定值符合要求。

9)温度计信号接点动作正确,膨胀式信号温度计的金属软管弯曲半径不小于60mm,不得有压扁或扭曲。

10)保护、测量、信号及控制回路的接线正确可靠,保护装置传动试验正确。11)试验项目齐全,试验结果符合规范和出厂要求。

……

6.2.2 变电站土建工程验收重点及要求 ……

7质量验评及初检报告

【编写说明】 根据质量验评的规范,描述对监理验评的具体要求和应完成的记录、报告。【示例】

(1)本次初检工作与工程质量验评工作结合进行。按照已审批的《××工程质量验评范围划分表》进行验评。初检中重点抽检的分项工程个数要求≥30%。

(2)初检工作结束,消缺完成并经验收小组复查确认后,由监理根据初检数据和带电投运试运情况核实线路、土建、电气分项工程、分部工程、单位工程的质量等级,并形成验评报告。(3)初检工作完成后,各验收小组提出书面初检意见,最后形成初检报告,并上报业主。

…… 安全措施

【编写说明】 针对验收工作内容和工作范围,按国家电网公司安全要求,列出本次初检应做的安全措施和验收过程中应做的安全措施,以及工作中的安全防护注意事项,对于系统试验等还应设专人值守和专人协调。【示例】

(1)验收前,验收组要向验收人员交代安全注意事项,同时施工单位应向验收人员进行交底,说明哪些设备、回路已带电,哪些操作需在验收配合人员的指导下进行,防止人员触电和设备、元器件的损坏。

(2)验收前已带电的一次设备,施工单位要设置隔栏,并悬挂标示牌。

(3)各验收人员应加强沟通、协调,交叉验收工作(如:高压试验、保护传动试验)

一、二次验收人员须协商一致后进行,避免出现意外。

(4)传动试验中如须跳合断路器,验收人员与施工单位须协商一致,在保证验收质量的前提下,尽量减少跳合次数,防止开关机械寿命的减少和元器件的损坏。

(5)全体验收人员要正确佩戴安全帽,着装规范,登高验收须正确使用靠梯、安全带、高空作业车等用具,并配备人员协助和监护。

(6)一次设备操作须在验收配合人员的指导和同意下进行,二次保护传动及监控遥控操作双方共同协商进行。

(7)验收中所动的一、二次回路接线头要及时正确恢复,机构箱门、端子箱门、盘柜门、盖板等要及时关闭,验收后不需继续通电的回路、装置、设备等施工单位要及时断电。(8)遵守交通法规,注意行车安全。(9)全体验收人员验收中要注意成品保护。…… 9

附表

【编写说明】 应附记录表、缺陷统计表、监理工程师通知单、监理工程师回复单等。

第五篇:电力线路监理初检方案(架线)

SBDJBSM20 架线(总体)工程监理初检方案

xxxxxxx220kV送出工程

监理初检方案

xxxx220kV送出工程监理项目部

201x年xx月

批准:审核:编写: 年 月 日年 月 日年 月 日

目 录

1.工程概况„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„116 1.1.工程规模及建设情况„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„116 1.2.工程参建单位„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„ „116 2.验收依据„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„116 3.验收范围及条件„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„116 3.1.验收范围„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„116 3.2.验收条件„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„116 4.验收组织机构及人员职责„„„„„„„„„„„„„„„„„„„„„„„„„„„„„117 4.1.验收组织机构设置„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„117 4.2.验收人员职责„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„117 4.3.验收资源配置„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„117 5.验收时间安排„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„118 6.验收要求„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„118 6.1.收总体要求„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„118 6.2.分部工程验收要求„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„119 7.质量验评及竣工初检报告„„„„„„„„„„„„„„„„„„„„„„„„„„„„„121 8.安全措施„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„121 9.附表„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„121 1 工程概况

1.1 工程规模及建设情况

1.1.1 建设地点: 1.1.2 线路长度: 1.1.3杆塔数量:

1.1.4 导地线型号及架设方式: 1.1.5 接地型式: 1.1.6 地形、地质: 1.1.7 主要气象条件: 1.1.8 绝缘子:

1.1.9 阐述各个分部工程具体实施情况: 1.2 工程参建单位

建设单位: 建设管理单位: 设计单位: 监理单位: 施工单位:

运行单位: 2 验收依据

2.0.1《建设工程监理规范》(GB50319-202_)。

2.0.2《110~500kV架空电力线路施工验收规范》(GB50233-202_)。2.0.3《钢结构工程施工及验收规范》(GB50205-202_)。

2.0.4《电力金具试验方法 第1部分:机械试验》(GB/T2317.1-202_)。2.0.5《园型同心绞架空导线》(GB/T 1179-202_)。

2.0.6《110~500kV架空电力线路工程施工质量及评定规程》(DL/T5168-202_)。2.0.7《110kV及以上送变电工程启动及竣工验收规程》(DL∕T782-202_)。2.0.8《电力建设工程监理规范》(DL/T5434-202_)。

2.0.9《国家电网公司输变电工程达标投产考核办法》(国家电网基建[202_]146号)。2.0.10《输变电工程建设标准强制性条文实施管理规程》(Q/GDW 248-202_)。2.0.11《国家电网公司工程建设质量管理规定》(国家电网基建〔202_〕699号)。2.0.12《国家电网公司输变电工程标准工艺示范手册》〔202_年版〕。

2.0.13《国家电网公司电力建设工程施工质量监理管理办法》(国家电网基建〔202_〕166号)。

2.0.14《国家电网公司输变电优质工程评选办法》(国家电网基建[202_]148号)。2.0.15《架空送电线路导地线液压施工工艺规程》(SDJ226-87)。

2.0.16 《关于利用数码照片资料加强输变电工程安全质量过程控制的通知》(基建安全〔202_〕25号)。

2.0.17 《关于加强输变电工程施工过程质量控制数码采集与管理的工作要求》基建质量【202_】322。

2.0.18根据《国家电网公司输变电工程质量通病防治工作要求及技术措施》(基建质量﹝202_﹞19号)的要求,采取质量通病防治工作的监理预控和检查专项措施。6.1 监理单位工程质量通病防治工作责任

6.1.1 审查施工单位提交的《xxx220kV送出工程质量通病防治措施》,提出具体要求并编写《xxxx220kV送出工程质量通病防治控制措施》。

6.1.2 认真做好隐蔽工程和工序质量的验收签证,上道工序不合格时,不允许进入下一道工序施工。

6.1.3 对架线工程的重要工序和关键部位旁站监理,加强工程质量的平行检验,发现问题及时处理。

6.1.4 工程完工后,认真填写《xxx220kV送出工程合川电厂二期220kV送出工程质量通病防治工作评估报告》。

2.0.19 本工程的设计图纸及业主有关规定。3 验收范围及条件 3.1验收范围

3.1.1 本次验收实物为:

3.1.2内业资料检查:施工单位质量保证体系、施工过程记录、原材料的控制以及三级自检;监理项目部的策划文件、旁站记录以及过程监理控制资料等。3.2验收条件

3.2.1 施工单位按设计和规范要求完成相应施工,无明显缺陷和遗留项目。3.2.2 已完工程经过施工项目部三级自检合格,具备申报验收条件。

3.2.3 施工单位应提交的竣工资料基本整理完毕,齐全有效,能够满足验收条件。3.2.4 监理单位收到施工项目部填报的《工程竣工报验单》及相关自检记录。4 验收组织机构及人员职责 4.1 验收组织机构设置

根据验收范围和验收工作内容,成立“xxx220kV送出输电线路工程初检验收组”,验收组名单如下:

组 长: 副组长: 组 员:

配 合:(施工单位人员)4.2 验收人员职责

4.2.1 初检验收组组长、副组长职责:负责统筹安排初验收工作,协调处理施工、运行、监理、设计、厂家等各方关系及验收中出现的重大事宜、争议。负责验收前的安全交底和组织召开每日的验收汇总会,听取各验收小组的工作汇报,总结每日验收工作,对验收中发现的缺陷提出整改指导意见,督促消缺,审核确认验收记录及验收报告。

4.2.2 各验收小组组长职责:组织本小组人员按验收范围及要求进行各专业工程验收,搜集、汇总验收缺陷及问题,消缺完成后,组织人员复查确认,填写验收记录及验收报告。

4.2.3 各验收小组副组长职责:负责本小组内验收人员的招集、管理以及现场安全监护工作,组织、参与验收工作,提出验收缺陷及问题,消缺完成后,参与复查、确认。

4.2.4 各验收小组组员职责:在小组组长的领导下,具体负责各自范围的验收工作及消缺复查工作。

4.2.5 各验收小组配合人员职责:对各小组验收工作进行全面配合,包括资料提供、工器具提供、后勤保障、配合具体的作业工作等。4.3 验收资源配置

验收人员所需的钢卷尺x把、经纬仪x台、计算器x个、电阻测量仪x个、交通车辆x台、移动电话x部、登塔检查所需的安全用具x付;相应的规程和规范技术文件。5 验收时间安排

验收时间201x年xx月xx日至201x年xx月xx日; 复检时间201x年xx月xx日至201x年 xx月xx 日。6 验收要求 6.1 验收总体要求

6.1.1 初检验收坚持现场实物检查与资料核查相结合,全面检查与重点抽查相结合的原则,既要检查现场实体质量,也要核查相关资料情况,既要重点抽查一些项目,也要对验收范围内的项目做全面检查,做到验收覆盖面100%,不漏项。

6.1.2 各验收小组要根据分工和工程施工完成情况,合理安排工作进度,保证验收工作安全、有序进行。

6.1.3 各验收人员要充分熟悉设计图纸、技术规范书和相关专业的有关标准、规范,熟悉材料/设备性能、参数和设备装置的原理。

6.1.4 验收用仪器仪表施工前应核查符合相关要求保证完好、有效。

6.1.5 验收人员必须严格执行验收规范,按照设计图纸认真验收,严格把关,确保验收质量。要认真填写质量检查验收记录,发现问题先与施工配合人员充分沟通,然后及时填写“工程质量检查及缺陷处理记录”。此记录表每天汇总一次,交施工单位及时进行消缺。

6.1.6 验收前,施工单位应向验收组提供下列主要资料及文件: ⑴ 主要施工技术资料。⑵ 主要施工技术记录。⑶ 质量检验、调试记录。⑷ 出厂资料、试验资料。⑸ 材料/构配件开箱记录。

⑹ 制造厂提供的出厂原始资料,即产品说明书、出厂试验记录、合格证及出厂图纸等。

6.2 分部工程验收要求

6.2.1铁塔及接地部分验收重点及要求

⑴ 铁塔平面结构及接点间不应有明显的鼓肚和凹陷,相邻节点接点间的主材弯曲不就超过节点间距的1/800。⑵ 直线塔的结构倾斜应控制在1‟以内,而张塔或直线转角塔应有预编,预编值应能保证架线后不向受力侧倾斜。

⑶ 塔材交叉铁处应装有垫块,其厚度应与主材厚度相符。

⑷ 铁塔塔材的部件规格及螺栓等规格必须符合图纸,铁塔不得有缺件。

⑸ 铁塔螺栓穿向应符合要求,螺栓坚固率M16不应小于82N²m,M20不应小于100N²m,M24不应小于250N²m,螺栓紧固率要大于97%。

⑹ 螺栓与螺帽有滑扣或螺帽棱角有磨损以致扳手打滑的螺栓或螺母必须更换。⑺ 螺栓的螺杆必须与构件面垂直并紧密接触,螺栓不应斜穿,螺栓紧固带防罩后应露出螺杆丝扣两个螺距,双帽者(含带防盗螺栓)至少应平母。

⑻ 塔材不得有流黄水现象,塔材表面麻面面积不应超出塔材表面总面积内外侧的10%,塔材镀锌层不允许有面积超过100mm2脱落,小于100mm2脱落只允许有一处,并应用环氧富锌漆进行防锈处理。

⑼ 保护帽制作符合设计要求。

⑽ 接地引下线应紧贴主材,连接应接触良好,制作工艺美观。6.2.2 紧线质量验收要求

⑴ 对交叉跨越物及对地距离应符合规范要求。

⑵ 紧线后导地线弧垂:110kV应不超过+4%、-2%;220kV及以上应不超过±2%;大跨越不应超过±0.8%,最大0.8m。

⑶ 紧线后导地线相间驰度差:110kV应不大于150mm;220kV及以上应不大于250mm;大跨越应不大于400mm。

⑷ 同相子导线弧垂差:无间隔棒双分裂不超过+100mm,0;有间隔棒其他分裂形式导线220kV不超过80mm;330kV~500kV不超过50mm。(工程有才编写)

⑸ 导地线弧垂线间距均匀协调美观。6.2.3 导地线液压连接

⑴ 压接管规格、型号应符合设计要求。

⑵ 压后尺寸应符合S=0.866³(0.993D)+0.2要求。

⑶ 接续管、耐张线夹压后检查管体无损伤,外观无飞边、毛刺,弯曲度应小于1.6%。⑷ 对各种压接管位置的控制:

1)各类管与耐张线夹出口间的距离不应小于15m。2)接续管或补修管与悬垂线夹中心的距离不应小于5m。3)接续管或补修管端部与间隔棒中心的距离不宜小于0.6m。6.2.4 附件安装

⑴ 绝缘子、金具及间隔棒规格、数量符合设计要求,绝缘子应干净、无损伤。⑵ 跳线及带电导体对杆塔电气间隙符合设计要求。⑶ 开口销及弹簧销应齐全并开口。⑷ 跳线制作应曲线平滑美观,无扭曲。

⑸ 悬垂绝缘子串倾斜不得超过4°(最大150mm)。⑹ 防振锤及阻尼线安装距离误差不得超过±24mm。⑺ 铝包带缠绕应统一、美观并符合规范要求,当并沟线夹的沟槽若与导线直径不匹配,无法夹紧时,也应缠绕铝包带。

⑻ 绝缘避雷线放电间隙不得超过±2mm。

⑼ 间隔棒的安装距离应按标准档距划分,因线路转角引起的线长偏差归入转角塔前后侧的端次档内(对耐张塔端次档距应以线路中心线为准)。杆塔两侧第一个间隔棒的安装距离偏差不应大于端次档距的±1.2%;其余不应大于次档距的±2.4%。

⑽ 绝缘子瓶口朝向应一致。瓶口偏离连串中心线不应超过1/4瓶口宽度。⑾ 屏蔽环、均压环绝缘间隙不超过±8mm。6.2.5 光缆架设

光缆架设应符合《规范》第7.7条光缆架设章节、光缆图纸设计交底及图纸会审纪要和供货商OPGW《光缆金具安装手册》、《安装技术指导书》的要求、《OPGW施工工艺要求》。施工作业过程中要接受技术督导的指导和要求。7 质量验评及竣工初检报告

7.1.1 本次初检工作与工程质量验评工作结合进行。按照已审批的《合川电厂二期220kV送出输电线路工程质量验评范围划分表》进行验评。初检重点抽检的分项工程个数要求大于30%。

7.1.2 初检工作结束,消缺完成并经验收小组复查确认后,由监理根据初检数据核实线路分项工程、分部工程、单位工程的质量等级,并形成验评报告。

7.1.3 初检工作完成后,各验收小组提出书面初检意见,最后形成初检报告,并上报业主。8 安全措施

8.1.1 交通安全:在交通行驶途中,驾乘人员必须遵守交通规则。路况不好的山路,验收杆塔的位置如车辆到达困难,验收人员不得强行要求驾驶员继续前行。

8.1.2 如线路位于山区,验收人员在行驶途中必须做好防滑措施;配备相应的药品和工具防止被野兽、毒蛇伤害;在林区验收的人员严禁吸烟,防止发生火灾。如线路靠近公路验收人员应在人行横道行走,不得横穿公路。

8.1.3 登高验收人员必须正确使用个人安全防护用品,防止高空坠落;如验收段有跨越高等级电压线路,应在两侧加挂接地线,防止感应电伤人;明确每组的小组长为安全监护人。9 附件